Cause:

Actual amount on one or more of the lines exceeds the corresponding allowed amount

estimateline

 



Solution:

Click in the Create Overage box to create an overage in Order Entry for the difference between the actual and allowed.  If selected system creates an overage, a different customer name can be selected to be used for the overage.  That way, original order  is billed to one company or person, and have the additional amounts billed to a second company or person, builder upgrade.

If option is not selected, the entire Actual Costs amount will be exported to the order.



Details:

Creating an Overage during Export

overage

This message is displayed when the actual amount on one or more of the lines exceeds the corresponding allowed amount.  Click in the Create Overage box to create an overage in Order Entry for the difference between the actual and allowed.  If selected system creates an overage, a different customer name can be selected to be used for the overage.  That way, original order  is billed to one company or person, and have the additional amounts billed to a second company or person, builder upgrade.

If option is not selected, the entire Actual Costs amount will be exported to the order.



Symptoms:Specify Overage Parameter when exporting Estimate to Order Entry

Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

0 comments

Article is closed for comments.