Manually Entered Capacities / Number of Crews Available / Auto Deduct

 System Options

 Calculate Installation Depot Maximum Capacity Based On  Manually Entered Depot Capacities
 View Installation Depot Capacities By  Number of Crews Available
Deduct Crews from Installation Depot Capacities Based On  Automatically Deduct Calculate Based on Line Quantities

Overview

Capacity for Specific Date for Installation Depot  =

Installation Total Depot Capacity -  Crew Assigned Deduction  -  No Crew Assigned Deduction  -  No Crew Assigned Crossover Deduction 

Depot Capacities are NOT based on Daily Qty Limit or Jobs Per Day entered for individual Crews. 

Amount Deducted from Depot Capacities IS based on Daily Qty Limit entered for individual Crews. 

Amount Deducted from Depot Capacities is NOT based on Crew Time Off data. 

Crossover Deduction Analysis will be NOT done. 

Only lines with a Deduct Capacity green checkmark and scheduled units > 0 will be considered.

Installation Depot Total Capacity 

ALL - Manually Entered Total Number of Crews for DOW 

Job Type  - Manually Entered Total Number of Crews for Job Type for DOW 

Crew Assigned Deduction

ALL - For each Job Type the following will be calculated and subtracted from the All Tab

  • For Jobs where Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Assigned
  • Sum(Line Qty / Crew's Daily Qty Limit for Line Job Type)

Job Type - The following will be calculated and subtracted from the Job Type Tab Available Capacity

  • For Jobs where Job Type = Job Type Tab and Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Assigned
  • Sum(Line Qty / Crew's Daily Qty Limit for Line Job Type) 

No Crew Assigned Deduction

ALL - For each Job Type the following will be calculated and subtracted from the All Tab

  • For Jobs where Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Not Assigned
  • Sum(Line Qty / Average Crew Daily Qty Limit for Line Job Type) 

Job Type - The following will be calculated and subtracted from the Job Type Tab Available Capacity

  • For Jobs where Job Type = Job Type Tab and Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Not Assigned
  • Sum(Line Qty / Average Crew Daily Qty Limit for Line Job Type) 

No Crew Assigned Crossover Deduction

NA for these system options 

Other Formulas

Average Crew Daily Qty Limit = Total Daily Qty Limit for Crews installing Job Type) / Number of Crews installing Job Type

 