System Options
| Calculate Installation Depot Maximum Capacity Based On | Manually Entered Depot Capacities |
| View Installation Depot Capacities By | Quantity Available |
| Deduct Crews from Installation Depot Capacities Based On | NA |
Overview
Capacity for Specific Date for Installation Depot =
Installation Total Depot Capacity - Crew Assigned Deduction - No Crew Assigned Deduction - No Crew Assigned Crossover Deduction
Depot Capacities are NOT based on Daily Qty Limit or Jobs Per Day entered for individual Crews.
Amount Deducted from Depot Capacities is NOT based on Daily Qty Limit or Jobs Per Day entered for individual Crews.
Amount Deducted from Depot Capacities is NOT based on Crew Time Off data.
Crossover Deduction Analysis will NOT be done.
Only lines with a Deduct Capacity green checkmark and scheduled units > 0 will be considered.
Installation Depot Total Capacity
ALL - Displays as % of Depot Capacity Left for Day
Job Type - Manually Entered Quantity Available for Job Type for DOW
Crew Assigned Deduction
ALL - For each Job Type the following will be calculated and subtracted from the All Tab
- For Jobs where Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Assigned
- Sum(Line Qty / Depot Daily Qty Limit for Line Job Type) * (1 / # of Job Types with Capacities Entered for Depot)
Job Type - The following will be calculated and subtracted from the Job Type Tab Available Capacity
- For Jobs where Job Type = Job Type Tab and Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Assigned
- Sum(Line Qty)
No Crew Assigned Deduction
ALL - For each Job Type the following will be calculated and subtracted from the All Tab
- For Jobs where Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Not Assigned
- Sum(Line Qty / Depot Daily Qty Limit for Line Job Type) * (1 / # of Job Types with Capacities Entered for Depot)
Job Type - The following will be calculated and subtracted from the Job Type Tab Available Capacity
- For Jobs where Job Type = Job Type Tab and Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Not Assigned
- Sum(Line Qty)
No Crew Assigned Crossover Deduction
NA for these system options