Automatically Calculated Capacities / Number of Crews Available / Manual Deduct

System Options

Calculate Installation Depot Maximum Capacity Based On Automatically Calculate Depot Capacities
View Installation Depot Capacities By Number of Crews Available
Deduct Crews from Installation Deport Capacities Based On Manually Enter Number of Crews to Deduct

Overview

Capacity for Specific Date for Installation Depot  =

Installation Total Depot Capacity  -  Crew Assigned Deduction  -  No Crew Assigned Deduction  -  No Crew Assigned Crossover Deduction 

Depot Capacities ARE based on Daily Qty Limit entered for individual Crews. 

Amount Deducted from Depot Capacities IS based on Daily Qty Limit entered for individual Crews.  Used only in Crossover Deduction. 

Amount Deducted from Depot Capacities IS based on Crew Time Off data.   Used only in Crossover Deduction. 

Crossover Deduction Analysis WILL be done. 

Only lines with a Deduct Capacity green checkmark and scheduled units > 0 will be considered. 

Total Crews Deducted for a Scheduled Job = Number of Lines * Manually Entered Number of Crews to Deduct 

DOW:  Capacities can be different for different days of the week. 

Installation Depot Total Capacity 

ALL - Total Number of Crews with a Daily Qty entered  for any Job Type for DOW 

Job Type  - Total Number of Crews with a Daily Qty entered  for Job Type for DOW 

Crew Assigned Deduction

ALL - Manually Entered Number of Crews to Deduct for All Jobs for Calendar Date for Depot where Crew Is Assigned 

Job Type - Manually Entered Number of Crews to Deduct for Job Type for Calendar Date for Depot where Crew Is Assigned 

No Crew Assigned Deduction

ALL - Manually Entered Number of Crews to Deduct for All Jobs for Calendar Date for Depot where No Crew Is Assigned 

Job Type - Manually Entered Number of Crews to Deduct for Job Type for Calendar Date for Depot where No Crew Is Assigned 

No Crew Assigned Crossover Deduction

All - Crossover Deduction is not calculated for the All Tab 

Job Type

  • For Each Cross Job Type (Job Type <> Job Type Tab) the following will be calculated and subtracted from the selected Job Type Tab 
  • For Jobs where Job Type <> Job Type Tab and Scheduled Install Date = Calendar Date and Job Depot = Current Depot and Crew = Not Assigned 
  • Total of Manually Entered Crews to Deduct for Cross Job Type * (Total Crew Daily Qty for Job Type Tab where Crew Installs Cross Job Type / Total of Crew Daily Qtys for Job Type Tab

Ex:  On the Tile Tab - For Each Job Type <> Tile calculate and subtract the following from the Tile Tab

Total of Manually Entered Crews to Deduct  for Carpet * ( Total Tile Daily Qty for all Crews that Install Carpet  / Total Tile Daily Qty for Crews )

Total of Manually Entered Crews to Deduct  for Hardwood* ( Total Tile Daily Qty for all Crews that Install Hardwood  / Total Tile Daily Qty for Crews )

Etc ...