WIP - Work In Progress Report

Sales Report>File> Finance>WIP

This report summarizes revenues and costs incurred to date with projected revenues and costs to complete the project for billing groups.

Purpose

Billing Group Progress

Data Source

Billing Group Order Lines

By Store

Y

By Sales Rep

N

By Product Code

Y

Profit

Projected

Customer Type

N

Balance Due

N

Order Status

Written and Delivered

.CSV output

Y

User Defined

N

Paper Size

8.5 X11

Balance to

 

Common uses:

 

Tips for Use:

Since this report pulls from line information, it does not include tax or miscellaneous cost in profit numbers. Load, freight, and overhead are also not included.

2019-05-02_15-59-26.jpg

The wording on the Work in Progress Report options screen was changed from Ending Date to Date to more accurately reflect that the date for this report determines how to group things on the report.

Listed below are the column headings of this report and where the numbers originate.

2019-05-02_16-00-57.jpg

Product         

Product Code

Contract Amount

Total Amount of all orders in the billing group

Change Orders

Amount of change orders.  NOTE:  This amount pulls from the lines on the change order.  The invoice has to be marked as a changed order in the billing group in order for this report to recognize the invoice as a change order and place the change order number on the report in this column.

Adjusted Total

Total of all invoices less any change orders.

Del. To Date

Total of all lines by product code that are in a job costed status.

Profit To Date

This number is calculated by taking the Delivered Net Sale amount and subtracting the following cost:

                                    Delivered Material Cost

                                    Delivered Service Cost

                                    Delivered Overhead Margin Cost

                                    Delivered Freight Cost

                                    Delivered Tax Cost

GP%

GP% is calculated on the delivered (job costed) portion of the sale.  To calculate the GP%: Profit to date \ Del. To Date = GP%

% Del.

% Delivered is how much of the job that has been billed so far. Delivered to Date / Contract Amount = % Delivered

Current Shipped

For Non-ERRM users, current shipped not job costed are lines on the Not Jobcosted order that a picking ticket has been run for. Therefore the lines are in a delivered status.

 

For ERRM users current shipped not job costed are lines on the order that a delivery ticket has been run for. Therefore the lines are in a delivered status.

Current Not Shipped

Current not shipped is the value of all lines in the billing group by product code that is not in a delivered or job costed status

Projected Cost

Undelivered

Cost of all lines by product code in the billing group which are not in a delivered or job costed status.

Projected Profit Undelivered

Projected profit on all lines in the billing group by Product code that is not in a delivered or job costed status.  To calculate the % undelivered profit: Contract Amount – Projected Cost = Projected Profit Undelivered

 