Job Cash Flow Report

The Job Cash Flow Report helps Commercial users monitor projects based on the cash flow activity. It provides visibility into how payments, costs, and budgets align throughout the project lifecycle.

Navigation: RFMS Navigator>Sales Reports>File>Sales>Job Cash Flow Report

mceclip0.png

Report Criteria

Environment

Included Orders

Non-ERRM

• Delivery Date is blank

• Invoice Print Date is not blank

ERRM

• Delivery Date is blank

• Age From Date is not blank

Report Options

Stores

  • Select the store(s) to include by single clicking on the store number(s).
  • To include all stores, click Tag All, tagall.gif.
  • Group By Store: Groups stores together in the report output.

Sales People

  • Select the salesperson(s) to include by single clicking on their name(s).
  • To include all, click the Tag All, tagall.gif.

Print Options

  • Print Preview: Preview this report before printing.
  • Break after Salesperson: Prints each salesperson's data on a separate page.
  • Output to CSV file To: Specify the location to save the report (e.g. c:\\Reports).

Report Columns

Each row in the report represents the totals of all orders meeting the criteria, aggregated by Ship To Name.

ColumnDescription
Invoice NumberMay represent multiple invoices sharing the same Ship To Name.
Budget SalesTotal of lines from Order Entry.
Budget CostTotal of costs from Order Entry.
Requisition

Total of order lines in Cut or Delivered status. Lines in Cut status are included regardless of billing status.

This value does not include lines in Gen PO, On Order, Reserve, or None status.

Notes:

  • As of version 22.99.2, this behavior is confirmed as intended.
  • PC00 lines contribute to Labor Costs and should be considered when analyzing total costs.
  • Staged lines are not reflected in the Requisition total until they move to an eligible status (e.g., Cut or Delivered).
  • For percentage-billed orders, ensure that payments are applied to the correct order to maintain accurate cash flow representation.
Balance to BillBudget minus billed amount.
Material Cost to DateMaterial cost of order lines in Gen PO, On Order, Reserve, Cut, or Delivered status. Does not include None status.
Labor Cost to DateLabor cost of provider records.
Projected CostsBudget minus (Material Cost + Labor Cost).
PaymentPayments made on the order.
Cash FlowPayments minus (Labor Cost to Date + Material Cost to Date).

Version Notes

  • Version 22.99.2: Confirmed that the Requisition column includes lines in Cut status regardless of billing status.
  • Current Behavior (Version 24 and later): Functionality remains the same.
Was this article helpful?
0 out of 0 found this helpful
Have more questions? Submit a request

Comments

0 comments

Article is closed for comments.